Construction continues moving forward along 34th Street as crews advance underground utility improvements throughout the corridor!
Last week, contractors installed new water main between Oak Park and Euclid avenues before advancing through the Euclid Avenue intersection. By Saturday, water main installation had continued east of Euclid Avenue toward, Wesley Avenue, marking another step forward as crews work their way through the eastern portion of the project corridor. |