Over the past two weeks, crews advanced installation of the new 8-inch water main east from East Avenue, working through the Gunderson Avenue intersection and continuing toward Ridgeland Avenue. This is a huge milestone as crews reach the eastern limits of the project area!
Along the way, crews installed new valve vaults, water valves, and fire hydrants and completed connections to the existing water mains at East and Gunderson Avenues. Last week alone, crews advanced the new water main approximately 850 feet, bringing installation closer to Ridgeland Avenue. |